Sec. 3.701Â Types and Numbers
Each building must have the following listed types and numbers of inspections performed by a qualified inspector:
(1)Â Building (5)Â Plan review and site inspectionÂ
  FoundationÂ
  FramingÂ
  Concrete - flat workÂ
  FinalÂ
  Â
(2)Â Electrical (3)Â Temporary PoleÂ
  Rough-inÂ
  FinalÂ
  Â
(3)Â Plumbing (3)Â Rough-inÂ
  Top-outÂ
  FinalÂ
  Â
(4)Â HVAC (2)Â Rough-inÂ
  FinalÂ
  Â
(5)Â Gas (2)Â Rough-inÂ
  FinalÂ
  Â
(6)Â Swimming Pool (3)Â Rough-in (Belly Steel)Â
  Deck (plumbing and electrical)Â
  FinalÂ
  Â
(7)Â Fence (2)Â Site reviewÂ
  FinalÂ
  Â
(8)Â Accessory Building (4)Â Plan (sketch) and siteÂ
  Foundation (if applicable)Â
  Electric and/or plumbing, if anyÂ
  FinalÂ
  Â
(9)Â Portable, move-in (3)Â Plan (sketch) and siteÂ
  Electrical/Plumbing, if anyÂ
  FinalÂ
  Â
(10)Â Miscellaneous (3)Â Plan (sketch) and siteÂ
  Sidewalk steelÂ
  FinalÂ
Sec. 3.702Â Inspections Required
(a)Â Building Inspections (5).
(1)Â Site inspection with plan review - prior to issuance of permit
(2)Â Foundation inspection (placement on lot, concrete forms, reinforcing steel, vapor barrier, etc.).
(3)Â Framing inspection (wood framing, anchoring, roof deck, etc.)
(4)Â Concrete flat-work (driveway approach, driveways, walkways, etc.).
(5)Â Final (fireplace, air vents, roofing, flashings, drainage, etc.).
(b)Â Electrical (3).
(1)Â Temporary pole (prior to starting construction).
(2)Â Rough-in (all wiring in place, and not covered up; main entrance and breaker box locations established).
(3)Â Final (all outlets wired, appliances connected, light bulbs installed, cover plates in place, etc.).
(c)Â Plumbing (8).
(1)Â Rough-in (all piping to be covered up under the building, water tested; may include house sewer and water service from meter to building.
(2)Â Top-out/stack-out (all above floor piping through the roof; includes fixture arms, etc.).
(3)Â Final (all fixtures set and working, water stops installed, outside hose bibs in place, etc.).
(d)Â Heating and Air Conditioning (2).
(1)Â Rough-in (duct-work, placement of heating unit, condensation drain, vents, etc.).
(2)Â Final (air outlet registers in place, ducts insulated, outside cooling unit installed correctly, etc.).
(e)Â Swimming Pool, Below Ground and Above Ground (3).
(1)Â Rough-in (underground plumbing and electrical, pool location on lot, drainage, etc.).
(2)Â Deck and belly steel.
(3)Â Final; finished plumbing (water heater, etc.) and electrical; safety barriers (fence, etc.).
(f)Â Fence (2).
(1)Â Site review
(2)Â Final - Survey stakes, fence in line with stakes, type and height of fence, clean-up, etc.
(g)Â Accessory Building (4) - Building on Lot.
(1)Â usually in conjunction with main building inspections (site and plan)
(2)Â foundation
(3)Â framing, roofing, etc.
(4)Â final
(h)Â Portable, Move-In (3).
(1)Â site and plan
(2)Â electrical and plumbing (if applicable)
(3)Â final
(i)Â Miscellaneous (3). Includes satellite antenna, hot-tub/spa, sidewalk, retaining wall, storm cellar, etc.
(1)Â plan/site
(2)Â sidewalk steel
(3)Â final
(Ordinance adopted 7/8/03)